Newfoundland and Labrador Hydro
2015 Interim Rates Application for Customers


The documents provided are for informational purposes only and are NOT the Official Board Record. Please read the
Board Disclaimer
before reviewing any information on this site.
APPLICATION
  Application
January 28, 2015 ~ NLH Interim Rates Application
May 27, 2015 ~ NLH Interim Rates Compliance Application
June 2, 2015 ~ NLH Interim Rates Compliance Application Supplementary Information
June 5, 2015 ~ Amended NLH Interim Rates Compliance Application
  


Correspondence
 
  February 4, 2015 ~ To Parties - Schedule
February 4, 2015 ~ NLH Correspondence 2015 Interim Rates Application
February 16, 2015 ~ IC - Request for Extension
February 16, 2015 ~ Boards Response to IC Request for Extension
February 17, 2015 ~ NLH - Evidentiary Clarification
February 18, 2015 ~ CA Submission
February 18, 2015 ~ NP Submission
February 18, 2015 ~ VALE Submission
February 18, 2015 ~ Further Extension Request from IC
February 18, 2015 ~ NLH Objection to IC Request for Extension
February 19, 2015 ~ CA Objection to IC Request for Extension
February 19, 2015 ~ To Parties - Response to IC Request for Extension
February 23, 2015 ~ IC Submission
February 25, 2015 ~ NLH Submission
March 11, 2015 ~ NLH Request to file reply submission by Monday March 23, 2015
March 17, 2015 ~ Geoff Young - Reply Submission
March 19, 2015 ~ IC No - Further Submissions
March 26, 2015 ~ LWHN - Submission
March 30, 2015 ~ NLH Reply to LWHN Submission of March 26, 2015
June 3, 2015 ~ To Parties - Boards Request to Hydro to Amend Application and Setting Schedule
June 11, 2015 ~ NP - No Comments - NLH 2015 Interim Rates Application - Compliance Application
June 12, 2015 ~ To Parties - NLH 2015 Interim Rates Compliance Application Extension for Hydros Reply to Comments from Parties
June 15, 2015 ~ To Parties - Interim-Rates-Compliance-App-Grant-Thorton-Report-and-Extension
June 15, 2015 ~ To Parties - CA Comments on Hydro's Amended Interim Rates Compliance Application
June 15, 2015 ~ To Parties - IC Comments on Hydro's Amended Interim Rates Compliance Application
June 15, 2015 ~ Vale Comments on Hydro's Amended Interim Rates Compliance Application
June 17, 2015 ~ NLH - Reply to Comments from Parties
  
RFI Questions  
  February 5, 2015 ~ Consumer Advocate - TIR-CA-NLH-1 to 9: Questions Only
February 5, 2015 ~ Vale Newfoundland and Labrador - TIR-V-NLH-1 to 2: Questions Only
February 6, 2015 ~ Island Industrial Customers - TIR-IC-NLH-1 to 6: Questions Only
February 6, 2015 ~ Newfoundland Power - TIR-NP-NLH-1 to 11: Questions Only
February 6, 2015 ~ Nunatsiavut Government - TIR-NG-NLH-1: Questions Only
February 6, 2015 ~ Public Utilities Board - TIR-PUB-NLH-1 to 15: Questions Only
March 5, 2015 ~ Public Utilities Board - TIR-PUB-NLH-16 to 20: Questions Only
  
Replies To RFI's  
  Public Utilities Board - Requests
Consumer Advocate - Requests
Island Industrial Customers - Requests
Newfoundland Power - Requests
Vale Newfoundland and Labrador - Requests
Nunatsiavut Government - Requests
  
Orders  
 
P.U 14 (2015)
P.U. 14 (2015)

P.U 16 (2015)
P.U. 16 (2015)

P.U 17 (2015)
P.U. 17 (2015)

  
Reports  
  June 11, 2105 - Grant Thornton - 2015 Interim Rates Compliance Application Report
   

PUB Home Page


Any questions, problems or comments concerning this page,

please contact
webmaster@pub.nl.ca