Newfoundland and Labrador Hydro
New Transmission Line Corridor from Bay d'Espoir
to Western Avalon
The documents provided are for informational purposes only and are NOT the Official Board Record. Please read the Board Disclaimer before reviewing any information on this site.
|
Application
|
|
New Transmission Line Corridor from Bay d'Espoir to Western Avalon
|
Notices
|
|
May 8, 2014 ~ Notice of Application - New Transmission Line Corridor from
Bay d'Espoir to Western Avalon
|
Correspondence
|
|
June 5, 2014 ~ Anemos Energy - Intervenors Submission
June 5, 2014 ~ CA - Intervenor Submission
June 5, 2014 ~ Danny Dumaresque - Intervenor Submission
June 5, 2014 ~ IC - Intervenor Submission
June 5, 2014 ~ Newfoundland Power - Intervenor Submission
June 5, 2014 ~ Vale - Intervenor Submission
June 27, 2014 ~ To Parties - Filing Schedule for RFIs
Oct 15, 2014 ~ To Parties - Setting Remaining Schedule
Oct 20, 2014 ~ IC - No Comments
Oct 20, 2014 ~ NP - No Comments
Oct 20, 2014 ~ DD - No Comments
Oct 23, 2014 ~ CA - No Comments
Oct 23, 2014 ~ To Parties - Remaining Schedule
Oct 31, 2014 ~ NP - Submission
Nov 5, 2014 ~ CA - Written Submission
Nov 5, 2014 ~ IC - Submission
Nov 5, 2014 ~ Vale - Comments
Nov 10, 2014 ~ NLH - Final Submission
|
RFI Questions
|
|
July 17, 2014 ~ IC-NLH-1 - IC-NLH-14: Questions Only
July 17, 2014 ~ PUB-NLH-1 - PUB-NLH-68: Questions Only
July 17, 2014 ~ CA-NLH-1 - CA-NLH-20: Questions Only
July 17, 2014 ~ DD-NLH-001 - DD-NLH-010: Questions Only
July 17, 2014 ~ NP-NLH-001 - NP-NLH-012: Questions Only
|
|
Replies to RFI's
|
|
Public Utilities Board - Requests
Industrial Customers - Requests
Consumer Advocate - Requests
Newfoundland Power - Requests
Danny Dumaresque - Requests
|
Board Orders
|
|
December 12, 2014 ~ PU 53 (2014)
|
|
|
PUB Home Page
Any questions, problems or comments concerning this page,
please contact webmaster@pub.nl.ca
|