Investigation and Hearing into Supply Issues and Power Outages on the Island Interconnected System

Intervenor Submissions
 
Jan 31, 2014: Island Industrial Customers - Intervenors Submission

Jan 31, 2014: Consumer Advocate - Intervenors Submission

Jan 31, 2014: Danny Dumaresque - Request for Intervenor Status

Feb 5, 2014: Danny Dumaresque - Intervenor Submission

Mar. 30, 2014 - Grand River Keeper Labrador Inc - Intervenor Submission


  Request from the Grand Riverkeeper Labrador Inc.


Mar. 7, 2014 - Letter to the Board from Grand Riverkeepers Labrador Inc. - Request for Intervenor                      Status

Mar. 13, 2014 - Board Letter to the Grand Riverkeepers Re Intervenor Request                     

Apr. 14, 2014 - To Parties - Request for Comments - Grand Riverkeeper Intervenor Status

Apr. 16, 2014 - NP Comments - GRK Intervenor Status

Apr. 22, 2014 - NLH Comments - GRK Intervenor Status

Apr. 23, 2014 - Comments on GRK Intervenor Status - Maurice Adams

Apr. 23, 2014 - CA Comments - GRK Intervenor Status

Apr. 23, 2014 - Grand Riverkeepers Letter to the Board Re NP and NLH Comments

Apr. 24, 2014 - Correspondence to the Parties - Enclosing Grand Riverkeepers Reply of Apr. 23, 2014

Apr. 30, 2014 - To Grand Riverkeeper Labrador Inc - Enclosing Order P.U 15 (2014)

May. 1, 2014 - To Grand Riverkeeper Labrador Inc. - Extension for Comments

 
 