P.U.  12 (2000-2001)

 

 

IN THE MATTER OF the

PUBLIC UTILITIES ACT,

R.S.N. 1990, c. P-47, as amended

(“the Act”)

                      AND

 

IN THE MATTER OF the application

by Newfoundland Power Inc. (“the

Applicant”) for approval of a contribution

in aid of construction (“CIAC”) for a line extension

to serve seasonal customers (“the Customers”)

pursuant to Section 41(5) of the Act.

 

 

 

 

WHEREAS the Applicant is a corporation duly organized and existing under the laws of the Province of Newfoundland and Labrador, is a public utility within the meaning of the Act, and is also subject to the provisions of the Electrical Power Control Act, 1994; and

 

WHEREAS the Customers are located on Beachy Cove Road near the community of Tors Cove  and consist of eleven Seasonal Customers; and

 

WHEREAS the Customers have requested that the Applicant provide their residences on Beach Cove Road with single phase electrical service which, in order to so provide, requires the construction  of  a single phase extension of 1,770 metres (the “Extension”); and

 

WHEREAS the Extension will not be jointly used by the Applicant and NewTel Communications Inc.; and

 

WHEREAS the Extension includes a 390 metre section of line extension with no customer premises contained thereon and Clause 5(e) of the distribution line CIAC Policy for Residential and Seasonal Residential Customers of the Applicant approved by Order No. P.U. 7 (1997-1998) dated the 30th day of September 1997 (the “Policy”) requires that this portion of the line be deemed a separate line extension; and

 

WHEREAS a CIAC for each separate line extension has been calculated in accordance with Clause 5(b) and Clause 5(c) of the Policy and the CIAC thus calculated is Three thousand seven hundred three dollars ($3,703.00), including HST, for the five customers located closest to the existing energized line (the “Group A customers”), and Five thousand three hundred ninety dollars and sixty-three cents ($5,390.63), including HST, for the six customers located beyond the continuous section of 390 metres with no customer premises located thereon (the “Group B customers”); and

 

WHEREAS the Applicant was of the understanding that the Customers were in agreement that both the Group A customers and the Group B customers would be included in the calculation of a CIAC of the Extension, on a cost averaged basis, and the Applicant quoted a CIAC to both groups of Four thousand six hundred twenty-three dollars and fifty-two cents ($4,623.52), including HST, and it subsequently became apparent that the financial impact of deviating from Clause 5(e) had not been communicated clearly to the Customers and Group A customers, once advised, were not in agreement with the inclusion of the Group B customers in the calculation of the CIAC, on a cost averaged basis; and

 

WHEREAS the Applicant is informed that some of the Group B customers have incurred expenses related to preparing their residences for electric service on the expectation that the CIAC  quoted initially would apply to them, and to address the expectation of these customers the Applicant proposes to deviate from the Policy by charging the Group B customers the average CIAC amount for the whole area ($4,623.52) and suspending the entitlement of Group B customers to refunds as calculated under Clause 6 of the Policy until the shortfall is recovered; and

 

WHEREAS the CIAC calculated from the Group B customers involves a deviation from the Policy and Clause 12(b) of the Policy states that all deviations from the Policy in the calculation of CIACs for Line extensions must be submitted to the Board for approval; and

 

WHEREAS Clause 12(c) of the Policy states that all CIACs for Main Line extensions for primarily seasonal residential customers be submitted to the Board for approval; and

 

WHEREAS the proposed CIAC is necessary to ensure that the Applicant’s investment in the Extension is compensatory over the useful life of the Extension and will not be to the detriment of the Applicant’s other customers; and


WHEREAS the proposed expenditures on the Extension are necessary for the Applicant to provide service and facilities to the Customers which are reasonably safe and adequate and just and reasonable as required pursuant to Section 37 of the Act; and

 

WHEREAS the Board is satisfied that the deviation from the requirements of Clause 5(e) of the Policy is reasonable in the circumstances.

 

 

IT IS THEREFORE ORDERED THAT:

 

Pursuant to Section 41(5) of the Act, the Board approves:

(a)    the CIAC in the amount of  Three thousand seven hundred and three dollars ($3,703.00), including HST, for the five Group A customers;

(b)   the  CIAC in the amount of Four thousand six hundred twenty-three dollars and fifty-two cents ($4,623.52), including HST, for the six Group B customers;

(c)    the suspension of refunds in accordance with Clause 6 of the Policy to the six Group B customers until the shortfall related to the deviation from the Policy is recovered.

 

                                                           

DATED at St. John’s, Newfoundland this 6th day of  July, 2000.

 

 

                                                                                                ________________________________

                                                                                                D.A. Vardy,

                                                                                                Chair & Chief Executive Officer.

 

                                                                                               

                                                                                                ______________________________

                                                                                                Darlene Whalen, P.Eng.,

                                                                                                Vice-Chairperson.

 

 

                                                                                                                                                           

                                                                                                G. Fred Saunders,

                                                                                                Commissioner.

 

__________________________

Barbara Thistle,

Assistant Board Secretary.

 Orders  /  Home