P.U. 15 (2000-2001)
IN THE MATTER OF the
PUBLIC UTILITIES ACT,
R.S.N. 1990, c. P-47, as amended
(“the Act”)
AND
IN THE MATTER OF the application
by Newfoundland Power Inc. (“the
Applicant”) for approval of a contribution
in aid of
construction (“CIAC”) for a line extension
to serve
NewTel Communications Inc.
(“the
Customer”) pursuant to Section 41(5)
of the Act.
WHEREAS the
Applicant is a corporation duly organized and existing under the laws of the
Province of Newfoundland and Labrador, is a public utility within the meaning
of the Act, and is also subject to the provisions of the Electrical Power Control Act, 1994; and
WHEREAS the
Customer will operate a telecommunications tower, located at Sheffield Lake,
west of Baie Verte Junction; and
WHEREAS the
Customer has requested that the Applicant provide its facility at Sheffield
Lake with single phase electrical service which, in order to so provide,
requires an upgrade of 7.5 km of
existing NewTel Communications line and the construction of 7.3 km of
additional single phase line (the “Extension”); and
WHEREAS the
upgraded portion only of the Extension will be jointly used by the Applicant
and NewTel Communications Inc.; and
WHEREAS a Contribution in Aid of Construction (“CIAC”)
of the Extension has been calculated in accordance with Clause 5 (f) of the
CIAC Policy; Distribution Line Extensions and Upgrades to General Service
Customers, approved by Order No. P.U. 7 (1997-98) dated the 30th day
of September 1997 (the “Policy”), which assumes the Extension will supply one
service with an estimated peak demand of less than 10 kW, and the CIAC thus
calculated is Two hundred twenty-eight thousand one hundred thirty dollars
($228,130.00), including HST; and
WHEREAS the CIAC was calculated in accordance with
Clause (f) of the Policy because the construction design standard to be
employed in the construction of the Extension is a different standard than the
one on which the average cost factors used in the Policy are based, and this
deviation from the Policy is necessary to avoid the over-recovery of costs from
the Customer; and
WHEREAS the
construction cost of the Extension is $202,831 and Clause 11(a) of the Policy
requires that all Line Extensions or Upgrades involving CIACs in which the
construction costs are estimated to be greater than $25,000 must be submitted
to the Board for approval; and
WHEREAS the proposed expenditures on the Extension are
necessary for the Applicant to provide service and facilities to the Customer
which are reasonably safe and adequate and just and reasonable as required
pursuant to s. 37 of the Act; and
WHEREAS the proposed CIAC is necessary to ensure that the
Applicant’s investment in the Extension is compensatory over the useful life of
the Extension and will not be to the detriment of the Applicant’s other
customers; and
WHEREAS the Board is satisfied that the deviation from the
Policy is reasonable in the circumstances and will not be to the detriment of
the Applicant’s other customers.
IT IS THEREFORE ORDERED THAT:
Pursuant to Section 41(5) of the Act, the Board approves
(a) the CIAC in the amount of Two hundred twenty-eight thousand one hundred thirty dollars ($228,130.00), including HST, as calculated under the Policy.
DATED at St. John’s, Newfoundland this 26th day of July, 2000.
________________________________
D.A. Vardy,
Chair & Chief Executive Officer.
______________________________
Darlene
Whalen, P.Eng.,
Vice-Chairperson.
G.
Fred Saunders,
Commissioner.
__________________________
G. Cheryl Blundon,
Board Secretary.