P.U. 19 (2000-2001)
IN THE MATTER OF the
PUBLIC UTILITIES ACT,
R.S.N. 1990, c. P-47, as amended
(“the Act”)
AND
IN THE MATTER OF the application
by Newfoundland Power Inc. (“the
Applicant”) for an Order rescinding
Order No. P.U. 13 (2000-2001), pursuant
to Section 76 of the Act, and approving a
revised contribution in aid of construction
(“CIAC”) for a line extension to serve
Seasonal Customers (the “Customers”)
pursuant to
Section 41(5) of the Act.
WHEREAS the
Applicant is a corporation duly organized and existing under the laws of the
Province of Newfoundland and Labrador, is a public utility within the meaning
of the Act, and is also subject to the provisions of the Electrical Power Control Act, 1994; and
WHEREAS the
Customers consist of sixty-one Seasonal Customers whose seasonal residences are
located in an area known as Second Junction Pond, Jack’s Pond and Whelan’s Pond
near Brigus Junction; and
WHEREAS by letter dated May 17, 2000, the Applicant quoted
a contribution in aid of construction (CIAC) in the amount of Five thousand
sixty dollars and forty-six cents ($5,060.46), including HST, as calculated
under the Contribution in Aid of Construction Policy: Distribution Line
Extensions to Residential and Seasonal Residential Customers approved by Order
No. P.U. 7 (1997-98) dated September 30, 1997 (the “Policy”), to 62 seasonal
customers who had expressed an interest in receiving electrical service; and
WHEREAS subsequent to the Applicant’s letter of May 17,
2000, the Applicant received written acceptance of the CIAC amount of $5,060.46
from 54 of the 62 seasonal customers listed in the Applicant’s letter of May
17, 2000, as well as from 7 additional seasonal customers not included in the
calculation of the original CIAC amount; and
WHEREAS the Applicant revised the calculation of the CIAC
amount on the basis of serving the 61 seasonal customers who had responded to
the Applicant’s letter dated May 17, 2000 and, on June 30, 2000, applied to the
Board for approval of the revised CIAC amount of Five thousand three hundred seventy-two dollars and forty-two
cents ($5,372.42), including HST, as calculated under the Policy (the “Revised
CIAC”); and
WHEREAS the Customers were not provided with written notice
of the Revised CIAC prior to submission of the application to the Board; and
WHEREAS the Board, by Order No. P.U. 13 (2000-2001),
approved the Revised CIAC; and
WHEREAS certain of the Customers who were not provided with
written notice of the increase in the amount of the CIAC have advised that they
are not willing to pay the higher amount, and this would result in a further
recalculation of the CIAC amount; and
WHEREAS the Applicant proposes to deviate from the Policy by
charging the Customers the CIAC amount initially quoted to the Customers rather
than the Revised CIAC approved by the Board in Order No. P.U. 13 (2000-2001),
which will create a shortfall in cost recovery of $311.96 per customer, and by
suspending the entitlement of the Customers to refunds as calculated under
Clause 6 of the Policy until that shortfall is recovered; and
WHEREAS the Extension will not be jointly used by the
Applicant and NewTel Communications Inc.; and
WHEREAS Clause 12(b) of the Policy requires that all
deviations from the Policy in the calculations of CIACs for Line extensions
must be submitted to the Board for approval; and
WHEREAS Clause 12(c) of the Policy requires that all CIACs
for Main Line extensions for primarily seasonal residential customers be
submitted to the Board for approval; and
WHEREAS the proposed suspension of refunds is necessary to
ensure that the Applicant’s investment in the Extension is compensatory over
the useful life of the Extension and will not be to the detriment of the
Applicant’s other customers; and
WHEREAS the Board is satisfied that the deviation from the
Policy is reasonable in the circumstances; and
WHEREAS the proposed expenditures on the Extension are
necessary for the Applicant to provide service and facilities to the Customers which
are reasonably safe and adequate and just and reasonable as required pursuant
to s. 37 of the Act.
IT IS THEREFORE ORDERED THAT:
2. Pursuant to Section 41(5) of the Act, the Board approves:
(a) the CIAC in the amount of Five thousand sixty dollars and forty-six cents ($5,060.46), including HST; and
(b) the suspension of the payment of refunds to the Customers until the shortfall of $311.96 per customer is recovered.
DATED at St. John’s, Newfoundland this 29th day of August, 2000.
________________________________
David A. Vardy,
Chair & Chief Executive Officer.
______________________________
Darlene
Whalen, P.Eng.,
Vice-Chairperson.
Raymond
A. Pollett,
Commissioner.
__________________________
Barbara Thistle,
Assistant Board Secretary.