P.U.  26 (2001-2002)

 

 

 

IN THE MATTER OF the

PUBLIC UTILITIES ACT,

R.S.N. 1990, c. P-47, as amended

(“the Act”)

                      AND

 

IN THE MATTER OF the application by

Newfoundland Power Inc. (“the Applicant”) for

approval of a contribution in aid of construction

for a line extension to serve the Town of Old Perlican

(“the Customer”) pursuant to section 41(5) of the Act.

 

 

 

 

 

WHEREAS the Applicant is a corporation duly organized and existing under the laws of the Province of Newfoundland and Labrador, is a public utility within the meaning of the Act, and is subject to the provisions of the Electrical Power Control Act, 1994; and

 

WHEREAS the Customer will operate a pumping station located near Old Perlican; and

 

WHEREAS the Customer has requested that the Applicant provide its facility with three-phase electrical service which, in order to so provide, requires the upgrade of 103 metres of two-phase line and 1,038 metres of single-phase line to three-phase standard and the construction of a further 60 metres of three-phase line (the “Extension”); and

 

WHEREAS the Extension will not be jointly used by the Applicant and Aliant Telecom Inc.; and

 

WHEREAS the maximum demand estimated for the Customer’s facility is less than 75 kW and in accordance with Regulation 5(b) of the Applicant’s Rates, Rules and Regulations approved by the Board from time to time, a contribution in aid of construction (“CIAC”) is required to cover the cost of transformers, equipment and any line extension of upgrade required to provide three-phase service and the CIAC thus calculated is reduced by the value of any single-phase plant supported by the projected revenue from the Customer; and

 

WHEREAS a CIAC of the Extension has been calculated in accordance with Clause 5(b) of the CIAC Policy:  Distribution Line Extensions and Upgrades to General Service Customers approved by Order No. P.U. 7 (1997-98) dated the 30th day of September, 1997 (the “Policy”), which calculation assumes the Extension will supply service to a pumping station with an estimated peak demand of  66.7 kW and the CIAC thus calculated is Eighteen thousand seven hundred and thirty-one dollars and sixty-six cents ($18,731.66), including HST; and

 

WHEREAS the construction cost of the Extension is $36,236.00 and Clause 11(a) of the Policy states that all Line Extensions or Upgrades involving CIACs in which the construction costs are estimated to be greater than $25,000 must be submitted to the Board for approval; and

 

WHEREAS the proposed expenditures on the Extension are necessary for the Applicant to provide service and facilities to the Customer which are reasonably safe and adequate and just and reasonable as required pursuant to s. 37 of the Act; and

 

WHEREAS the proposed CIAC is necessary to ensure that the Applicant’s investment in the Extension is compensatory over the useful life of the Extension and will not be to the detriment of the Applicant’s other customers.

 

 

IT IS THEREFORE ORDERED THAT:

 

Pursuant to Section 41(5) of the Act, the Board approves the CIAC of Eighteen thousand seven hundred thirty-one dollars and sixty-six cents ($18,731.66), including HST, as calculated under the Policy.

 

                                                           

DATED at St. John’s, Newfoundland, this 21st day of November, 2001.

 

 

                                                                                                ________________________________

                                                                                                Robert Noseworthy,

                                                                        Chair & Chief Executive Officer.

                                                                                               

                                                                                                ______________________________

                                                                                                Darlene Whalen, P.Eng.,

                                                                                                Vice-Chairperson.

 

 

__________________________

G. Cheryl Blundon,

Director of Corporate Services

  and Board Secretary.

Orders / Home