The Board has been requested by Government to undertake a review of electricity rate mitigation options and impacts in relation to the Muskrat Falls Project in accordance with the reference from the Lieutenant-Governor in Council under section 5 of the Electrical Power Control Act issued on September 5, 2018. The Board has been directed to review and report on: 1) options to reduce the impact of the Muskrat Falls Project costs on electricity rates; 2) the amount of required and surplus energy and capacity from the project; and, 3) the rate impacts of the identified options based on the most recent project cost estimates.

Government has appointed Dennis Browne, Q.C. as Consumer Advocate for the purposes of participating in this review. Mr. Browne may be contacted here

 


Correspondence
 
Letter from Minister Siobhan Coady, Department of Natural Resources - Muskrat Falls Rate Mitigation Reference Questions - September 7, 2018
Letter to Stan Marshall, CEO, Nalcor - September 24, 2018
Synapse Energy Economics Inc - Engagement Agreement - October 4, 2018
The Liberty Consulting Group - Engagement Agreement - October 5, 2018
Letter from Stan Marshall - CEO - Nalcor - October 19, 2018
Letter from McInnes Cooper - Disclosure of Information - November 19, 2018
Letter to McInnes Cooper - Disclosure of Information - November 23, 2018
Letter from McInnes Cooper - Disclosure of Information - December 4, 2018
Nalcor's Response to Expert Reports - January 9, 2019
Letter from Minister Siobhan Coady, Department of Natural Resources – Interim Report on Rate Mitigation Options and Impact - February 19, 2019
From Island Industrial Customer Group - Request for Standing - March 7, 2019
From NP - Request for Standing - March 8, 2019
From Ronald Penney - The Muskrat Falls Concerned Citizens Coalition - Request for Standing - March 11, 2019
From Robert R Beaudoin - Request for Standing - March 11, 2019
From Labrador Interconnected Customer Group - Request for Standing - March 12, 2019
To Robert Beaudoin - Request for Standing - March 13, 2019
To Labrador Interconnected Customer Group - Request for Standing - March 13, 2019
To NP - Request for Standing - March 13, 2019
To Island Industrial Customer Group - Request for Standing - March 13, 2019
To Ronald Penney - Request for Standing - March 13, 2019
From Ronald G. Penney - Response to Board March 13, 2019 Letter - March 18, 2019
To Ronald Penney - Response to March 18, 2019 Letter - March 21, 2019
From Ronald Penney - Response to Board March 21, 2019 Letter - March 24, 2019
To Ronald Penney - Response to March 24, 2019 E-mail - March 26, 2019
To Parties - Enclosing Rules of Procedure and List of Parties - March 26, 2019
To Parties - Draft Issues To Be Reviewed and Schedule and Process - April 3, 2019
To McInnes Cooper - Information Request PUB-Nalcor-093 - Withdrawn - April 11, 2019
To Parties - Issues List and Schedule - April 24, 2019
To Minister of Natural Resources - Rate Mitigation Options and Impacts Reference - April 25, 2019
To McInnes Cooper - IR - PUB-Nalcor-221-Revised - May 27, 2019
To Parties - Revised Schedule - August 1, 2019
From NP - Comments on Response to PUB-Nalcor-219 - August 6, 2019
To Parties - Request for Extension of Filing Parties' expert and non-expert reports - September 11, 2019
To Parties - Enclosing - Revised Schedule - September 11, 2019
To Minister of Natural Resources - Rate Mitigation Options and Impacts Reference - September 18, 2019
To Parties - Witness List - Areas-Topics Addressing - September 19, 2019
From CA - Non-expert Evidence - September 20, 2019
From NP - Expert and Non-expert Evidence - September 20, 2019
From Nalcor and Newfoundland and Labrador Hydro - Expert and Non-expert Evidence - Joint Submission - Witness List - September 20, 2019
From NP - Witness List - September 20, 2019
From IC - Expert Evidence of Patrick Bowman and Witness List - September 20, 2019
To Parties - Cover Letter - Synapse Phase Two Report - Revision 1 - September 25, 2019
To McInnes Cooper - Nalcor - Newfoundland and Labrador Hydro Evidence - Scope of Reference - September 26, 2019
To Parties - Cover Letter - Presentations - The Liberty Consulting Group and Synapse Energy Economics, Inc. - September 30, 2019
From Nalcor - Cover Letter - Stan Marshall - Presentation for Hearing - October 3, 2019
From Nalcor - Cover Letter - Power Advisory LLC - Presentation for Hearing - October 3, 2019
From Nalcor and Newfoundland and Labrador Hydro - Cover Letter - Panel 2 - Presentation for Hearing - October 8, 2019
From NP - Cover Letter - Presentation for Hearing - October 9, 2019
To McInnes Cooper - Nalcor - Revisions to Responses to Information Requests - November 20, 2019
To McInnes Cooper - Nalcor - Response to PUB-Nalcor-078 - Revision 1, December 4, 2019 - December 5, 2019
To Minister of Natural Resources - Rate Mitigation Options and Impacts Reference - Final Report Deadline - January 27, 2020
From Minister of Natural Resources - Rate Mitigation Options and Impacts Reference - Final Report Extension Granted - January 30, 2020